by Mitch Nolze | Jul 3, 2026 | Station 22 Renovation (ARCHIVE ONLY)
Community Members, It has been a long couple of years since our Sudden Valley fire station (Station 22) was damaged by a major pipe break. The timing was unfortunate that we were already preparing for a moderate renovation and replacement of a failing fire sprinkler...
by Mitch Nolze | Dec 16, 2025 | Station 22 Renovation (ARCHIVE ONLY)
Community members, It has been a while since our last update. Below is the update posted in our Winter 2025 community newsletter: The renovation project for Sudden Valley Fire Station 22 is under way. In accordance with public works project procurement laws, Tiger...
by Mitch Nolze | Sep 5, 2025 | Station 22 Renovation (ARCHIVE ONLY)
Community Members, I am happy to report that after a very long wait, and a lot of planning, construction is tentatively scheduled to start October 6, 2025 on the Sudden Valley Fire Station (Station 22)! Our public works bidding process closed on August 15th and...
by Mitch Nolze | Jul 22, 2025 | Station 22 Renovation (ARCHIVE ONLY)
Dear Sudden Valley Community, I know it has been frustrating not hearing any progress on the Sudden Valley Fire Station (Station 22), but unfortunately it has been a waiting game while over 400 pages of specifications, project plans, and bid package materials were...
by Mitch Nolze | Feb 11, 2025 | Station 22 Renovation (ARCHIVE ONLY)
Dear Community Members, It has been a while since we have provided any updates for the Sudden Valley Fire Station renovation/restoration project. This is simply because there have been no updates to provide. The architect and engineering firms have been working...
by Mitch Nolze | Sep 19, 2024 | Station 22 Renovation (ARCHIVE ONLY)
~FROM THE FIRE CHIEF~ Dear Community Members, I am happy to report that we are now under contract for the next phase of architectural design, permitting, and construction management for the remodel and restoration of the Sudden Valley Fire Station. While we have a...